PMI CAPM: Certified Associate in Project Management Sample Questions
Question 1: What document describes the way in which a project is executed, monitored, controlled, and closed?
- A. Strategic plan
- B. Project charter
- C. Project management plan
- D. Service level agreement
Correct Answer: C
Question 2: What changes occur as a typical project’s life cycle progresses in terms of risk and uncertainty, and how does it affect costs?
- A. Risk & uncertainty increase; cost of changes increases.
- B. Risk & uncertainty increase; cost of changes decreases.
- C. Risk & uncertainty decrease; cost of changes increases.
- D. Risk & uncertainty decrease; cost of changes decreases.
Correct Answer: C
Question 3: How do plan scope management tools and techniques work?
- A. Document analysis
- B. Observations
- C. Product analysis
- D. Expert judgment
Correct Answer: D
Question 4: In addition to examining the industry and specifics, which tool or technique is used for examining vendor capabilities?
- A. Independent estimates
- B. Market research
- C. Analytical techniques
- D. Bidder conferences
Correct Answer: B
Question 5: A communications management plan is developed based on the following inputs:
- A. Communication models.
- B. Enterprise environmental factors.
- C. Organizational communications.
- D. Organizational cultures and styles.
Correct Answer: B
Question 6: A regression analysis, a failure mode and effect analysis (FMEA), a fault tree analysis (FTA), or a trend analysis is among the tools or techniques used in regression analysis?
- A. Expert judgment
- B. Forecasting methods
- C. Earned value management
- D. Analytical techniques
Correct Answer: D
Question 7: In which Process Group does the Perform Quality Assurance process take place?
- A. Executing
- B. Monitoring and Controlling
- C. Initiating
- D. Planning
Correct Answer: A
Question 8: To which process are Enterprise environmental factors an input?
- A. Control Scope
- B. Define Scope
- C. Plan Scope Management
- D. Collect Requirements
Correct Answer: C
Question 9: In which process are options and actions developed for maximizing opportunities and reducing threats to the project’s goals developed?
- A. Identify Risks
- B. Control Risks
- C. Plan Risk Management
- D. Plan Risk Responses
Correct Answer: D
Question 10: The policies, procedures, and documents used for planning, defining, managing, executing, and controlling the project schedule are called:
- A. Plan Schedule Management.
- B. Develop Project Charter.
- C. Develop Schedule.
- D. Plan Scope Management.
Correct Answer: A
Question 11: How are changes that occur during the project documented as part of the Manage Stakeholder Engagement process?
- A. Issue log
- B. Change log
- C. Expert judgment
- D. Change requests
Correct Answer: B
Question 12: Which of the following is an input to the Plan Stakeholder Management process is:
- A. The project charter.
- B. The stakeholder analysis.
- C. A communication management plan.
- D. A stakeholder register.
Correct Answer: D
Question 13: Which of the following is an input to the Plan Cost Management process is:
- A. Cost estimates
- B. Resource calendars
- C. The project charter
- D. The risk register
Correct Answer: C
Question 14: Identifying the cause and degree of differences between baseline and actual performance can be done by using the following method:
- A. Product analysis.
- B. Variance analysis.
- C. Document analysis.
- D. Decomposition.
Correct Answer: B
Question 15: Developing a staffing management plan requires identifying roles, responsibilities, required skills, and reporting relationships for the project.
- A. Develop Project Team.
- B. Manage Project Team.
- C. Acquire Project Team.
- D. Plan Human Resource Management.
Correct Answer: D
Question 16: Does work involve physical limitations and is often legally or contractually required to involve dependency?
- A. Mandatory
- B. Discretionary
- C. Internal
- D. External
Correct Answer: A
Question 17: During what phase of the project management process does a project manager review all prior information to ensure the project’s objectives have been met?
- A. Monitor and Control Project Work
- B. Perform Quality Assurance
- C. Close Project or Phase
- D. Control Scope
Correct Answer: C
Question 18: Which of the following is an input to the Manage Project Team process is:
- A. Work performance reports.
- B. Change requests.
- C. Activity resource requirements.
- D. Enterprise environmental factors.
Correct Answer: A
Question 19: Which of the given input provides suppliers with a clear set of goals, requirements, and outcomes?
- A. Procurement statement of work
- B. Purchase order
- C. Source selection criteria
- D. Bidder conference
Correct Answer: A
Question 20: What Process Group is typically responsible for spending a large portion of a project’s budget?
- A. Executing
- B. Planning
- C. Monitoring and Controlling
- D. Closing
Correct Answer: B
Prepare for Assured Success
Want to become PMI Certified Associate in Project Management? Learn MoreAre you preparing for the PMI CAPM exam?Take a Quiz