PMI CAPM: Certified Associate in Project Management Sample Questions

  1. Home
  2. PMI CAPM: Certified Associate in Project Management Sample Questions
PMI CAPM Sample Questions
Question 1: What document describes the way in which a project is executed, monitored, controlled, and closed?
  • A. Strategic plan
  • B. Project charter
  • C. Project management plan
  • D. Service level agreement

Correct Answer: C

Question 2: What changes occur as a typical project’s life cycle progresses in terms of risk and uncertainty, and how does it affect costs?
  • A. Risk & uncertainty increase; cost of changes increases.
  • B. Risk & uncertainty increase; cost of changes decreases.
  • C. Risk & uncertainty decrease; cost of changes increases.
  • D. Risk & uncertainty decrease; cost of changes decreases.

Correct Answer: C

Question 3: How do plan scope management tools and techniques work?
  • A. Document analysis
  • B. Observations
  • C. Product analysis
  • D. Expert judgment

Correct Answer: D

Question 4: In addition to examining the industry and specifics, which tool or technique is used for examining vendor capabilities?
  • A. Independent estimates
  • B. Market research
  • C. Analytical techniques
  • D. Bidder conferences

Correct Answer: B

Question 5: A communications management plan is developed based on the following inputs:
  • A. Communication models.
  • B. Enterprise environmental factors.
  • C. Organizational communications.
  • D. Organizational cultures and styles.

Correct Answer: B

Question 6: A regression analysis, a failure mode and effect analysis (FMEA), a fault tree analysis (FTA), or a trend analysis is among the tools or techniques used in regression analysis?
  • A. Expert judgment
  • B. Forecasting methods
  • C. Earned value management
  • D. Analytical techniques

Correct Answer: D

Question 7: In which Process Group does the Perform Quality Assurance process take place?
  • A. Executing
  • B. Monitoring and Controlling
  • C. Initiating
  • D. Planning

Correct Answer: A

Question 8: To which process are Enterprise environmental factors an input?
  • A. Control Scope
  • B. Define Scope
  • C. Plan Scope Management
  • D. Collect Requirements

Correct Answer: C

Question 9: In which process are options and actions developed for maximizing opportunities and reducing threats to the project’s goals developed?
  • A. Identify Risks
  • B. Control Risks
  • C. Plan Risk Management
  • D. Plan Risk Responses

Correct Answer: D

Question 10: The policies, procedures, and documents used for planning, defining, managing, executing, and controlling the project schedule are called:
  • A. Plan Schedule Management.
  • B. Develop Project Charter.
  • C. Develop Schedule.
  • D. Plan Scope Management.

Correct Answer: A   

Question 11: How are changes that occur during the project documented as part of the Manage Stakeholder Engagement process?
  • A. Issue log
  • B. Change log
  • C. Expert judgment
  • D. Change requests

Correct Answer: B

Question 12: Which of the following is an input to the Plan Stakeholder Management process is:
  • A. The project charter.
  • B. The stakeholder analysis.
  • C. A communication management plan.
  • D. A stakeholder register.

Correct Answer: D

Question 13: Which of the following is an input to the Plan Cost Management process is:
  • A. Cost estimates
  • B. Resource calendars
  • C. The project charter
  • D. The risk register

Correct Answer: C

Question 14: Identifying the cause and degree of differences between baseline and actual performance can be done by using the following method:
  • A. Product analysis.
  • B. Variance analysis.
  • C. Document analysis.
  • D. Decomposition.

Correct Answer: B

Question 15: Developing a staffing management plan requires identifying roles, responsibilities, required skills, and reporting relationships for the project.
  • A. Develop Project Team.
  • B. Manage Project Team.
  • C. Acquire Project Team.
  • D. Plan Human Resource Management.

Correct Answer: D

Question 16: Does work involve physical limitations and is often legally or contractually required to involve dependency?
  • A. Mandatory
  • B. Discretionary
  • C. Internal
  • D. External

Correct Answer: A

Question 17: During what phase of the project management process does a project manager review all prior information to ensure the project’s objectives have been met?
  • A. Monitor and Control Project Work
  • B. Perform Quality Assurance
  • C. Close Project or Phase
  • D. Control Scope

Correct Answer: C

Question 18: Which of the following is an input to the Manage Project Team process is:
  • A. Work performance reports.
  • B. Change requests.
  • C. Activity resource requirements.
  • D. Enterprise environmental factors.

Correct Answer: A

Question 19: Which of the given input provides suppliers with a clear set of goals, requirements, and outcomes?
  • A. Procurement statement of work
  • B. Purchase order
  • C. Source selection criteria
  • D. Bidder conference

Correct Answer: A

Question 20: What Process Group is typically responsible for spending a large portion of a project’s budget?
  • A. Executing
  • B. Planning
  • C. Monitoring and Controlling
  • D. Closing

Correct Answer: B

CAPM free practice tests
Menu